| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | SWAT ANALYSIS | Er. Sivashankar Sivaraman | Completed |
| 2 | LEGAL DUE DILIGENCE | Er. Sivashankar Sivaraman, ADV. Bhamini Manogaran & ADV. Sathish Kumar | Completed |
| 3 | SOIL TESTING | Er. Manikandan Srinivasan | Completed |
| 4 | ARCHITECTURAL DRAWINGS | Er. Sivashankar Sivaraman, Er. Manikandan Srinivasan & Mr. Rengarajan - VR Architectures | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | ACQUISITION OF STRUCTURAL STABILITY REPORT | Er. Sivashankar Sivaraman & Mr. Prakash - VRP Structures | Completed |
| 2 | ACQUISITION OF BUILDING PERMIT | Er. Sivashankar Sivaraman | Completed |
| 3 | SITE MARKING | Mr. Sivashankar Sivaraman | Completed |
| 4 | BORE WELL | Mr. Sivashankar Sivaraman | Completed |
| 5 | ACQUISITION OF FOUNDATION ARCHITECTURAL & STRUCTURAL DRAWINGS | Sivashankar Sivaraman & Mr. Prakash - VRP Structures | Completed |
| 6 | POOJA | Not Applicable | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | PILLING FOR FOUNDATON | TBC | |
| 2 | CONCRETING FOR FOUNDATION | TBC | |
| 3 | ACQUISITION OF BASEMENT ARCHITECTURAL & STRUCTURAL DRAWINGS | TBC | |
| 4 | ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS | TBC | |
| 5 | PILE CAP FABRICATION & SHUTTERING | TBC | |
| 6 | PILE CAP CONCRETING | TBC | |
| 7 | INSTALATION OF UG SUMP | TBC | |
| 8 | ESCAVATION | TBC | |
| 9 | Structural Inspection | TBC | |
| 10 | PLINTH BEAM | TBC | |
| 11 | BLOCK WORK | TBC | |
| 12 | TIE BEAM | TBC | |
| 13 | EARTH FILLING | TBC | |
| 14 | FLOOR CONCRETING | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | STEEL FABRICATION COLUMNS | TBC | |
| 2 | COLUMN MARKING FOR CONCRETING | TBC | |
| 3 | COLUMN CONCRETING | TBC | |
| 4 | ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS | TBC | |
| 5 | STAIRCASE MARKING | TBC | |
| 6 | FABRICATION FOR BEAM | TBC | |
| 7 | SHUTERING FOR ROOF SLAB | TBC | |
| 8 | FABRICATION FOR ROOF SLAB 1 | TBC | |
| 9 | Structural Inspection | TBC | |
| 10 | CONCRETING FOR ROOF SLAB | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | STEEL FABRICATION COLUMNS | TBC | |
| 2 | COLUMN MARKING FOR CONCRETING | TBC | |
| 3 | COLUMN CONCRETING | TBC | |
| 4 | ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS | TBC | |
| 5 | STAIRCASE MARKING | TBC | |
| 6 | FABRICATION FOR BEAM | TBC | |
| 7 | SHUTERING FOR ROOF SLAB | TBC | |
| 8 | FABRICATION FOR ROOF SLAB 2 | TBC | |
| 9 | Structural Inspection | TBC | |
| 10 | CONCRETING FOR ROOF SLAB | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | STEEL FABRICATION COLUMNS | TBC | |
| 2 | COLUMN MARKING FOR CONCRETING | TBC | |
| 3 | COLUMN CONCRETING | TBC | |
| 4 | ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS | TBC | |
| 5 | STAIRCASE MARKING | TBC | |
| 6 | FABRICATION FOR BEAM | TBC | |
| 7 | SHUTERING FOR ROOF SLAB | TBC | |
| 8 | FABRICATION FOR ROOF SLAB 3 | TBC | |
| 9 | Structural Inspection | TBC | |
| 10 | CONCRETING FOR ROOF SLAB | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | STEEL FABRICATION COLUMNS | TBC | |
| 2 | COLUMN MARKING FOR CONCRETING | TBC | |
| 3 | COLUMN CONCRETING | TBC | |
| 4 | ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS | TBC | |
| 5 | STAIRCASE MARKING | TBC | |
| 6 | FABRICATION FOR BEAM | TBC | |
| 7 | SHUTERING FOR ROOF SLAB | TBC | |
| 8 | FABRICATION FOR ROOF SLAB 4 | TBC | |
| 9 | Structural Inspection | TBC | |
| 10 | CONCRETING FOR ROOF SLAB | TBC | |
| 11 | Architecural Inspection | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Marking for Block Work Level 1 | TBC | |
| 2 | Sil & Windows Markings Level 1 | TBC | |
| 3 | Blockwork Execution Level 1 | TBC | |
| 4 | Laying of Lintel Beam Level 1 | TBC | |
| 5 | Super Structure Block Work Level 1 | TBC | |
| 6 | Marking for Block Work Level 2 | TBC | |
| 7 | Sil & Windows Markings Level 2 | TBC | |
| 8 | Blockwork Execution Level 2 | TBC | |
| 9 | Laying of Lintel Beam Level 2 | TBC | |
| 10 | Super Structure Block Work Level 2 | TBC | |
| 11 | Marking for Block Work Level 3 | TBC | |
| 12 | Sil & Windows Markings Level 3 | TBC | |
| 13 | Blockwork Execution Level 3 | TBC | |
| 14 | Laying of Lintel Beam Level 3 | TBC | |
| 15 | Super Structure Block Work Level 3 | TBC | |
| 16 | Instalation of Door Frame (Level 1, Level 2 & Level 3) | TBC | |
| 17 | Structural Stability Inspection | TBC | |
| 18 | Architecural Inspection | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | INSTALATION OF LIFT - Stage 1 | TBC | |
| 2 | ELECTRICAL PIPING & CONDUIT - Level 1 | TBC | |
| 3 | Fixing of Switch Metel Box, Distibution Box & Electrical Fixtures - Level 1 | TBC | |
| 4 | ELECTRICAL PIPING & CONDUIT - Level 2 | TBC | |
| 5 | Fixing of Switch Metel Box, Distibution Box & Electrical Fixtures - Level 2 | TBC | |
| 6 | Instalation of Door Frame internal Door & Washroom Doors (Level 1, Level 2, Level 3) | TBC | |
| 7 | ELECTRICAL PIPING & CONDUIT - Level 3 | TBC | |
| 8 | Fixing of Switch Metel Box, Distibution Box & Electrical Fixtures - Level 3 | TBC | |
| 9 | Button Marking for Plastering (Level 1, Level 2, Level 3) | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Internal Plastering - Level 1 | TBC | |
| 2 | Internal Plastering - Level 2 | TBC | |
| 3 | Internal Plastering - Level 3 | TBC | |
| 4 | Comon Area Platering (Level 1, Level 2, Level 3) | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Instalation of Main Door - (Level 1, Level 2, Level 3) | TBC | |
| 2 | Internal Putty - (Level 1, Level 2, Level 3) | TBC | |
| 3 | Internal Primer Coat 1 - (Level 1, Level 2, Level 3) | TBC | |
| 4 | Internal Primer Coat 2 - (Level 1, Level 2, Level 3) | TBC | |
| 5 | Construction of parapet wall | TBC | |
| 6 | Inspection before plastering | TBC | |
| 7 | External Platering South Side | TBC | |
| 8 | External Platering West Side | TBC | |
| 9 | External Platering East Side | TBC | |
| 10 | External Platering North Side | TBC | |
| 11 | Instalation of internal Plumibing | TBC | |
| 12 | Internal Wiring - (Level 1, Level 2, Level 3) | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Instalation Water Tank | TBC | |
| 2 | Instation of Florring - (Level 1, Level 2, Level 3) | TBC | |
| 3 | External Plumbig | TBC | |
| 4 | Instation of Internal and Washroom Doors | TBC | |
| 5 | Instation of Windows and Grills | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Marking for Compund wall | TBC | |
| 2 | Escavation of Compund Coloumns | TBC | |
| 3 | Fabrication for Footing | TBC | |
| 4 | Footing Concreting | TBC | |
| 5 | Fabrication for Column | TBC | |
| 6 | Compound Callumn Concreting | TBC | |
| 7 | Block Work for Column | TBC | |
| 8 | Compund Plastering | TBC | |
| 9 | Instation of Pavor Block in Car Parking | TBC | |
| 10 | Appliying for power connection for all booked customers | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Internal Painting (Level 1, Level 2 & Level 3) | TBC | |
| 2 | Door Painting | TBC | |
| 3 | Grill Painting | TBC | |
| 4 | External painting | TBC | |
| 5 | Instalation of CCTV Cameras | TBC | |
| 6 | Landscaping | TBC | |
| 7 | Instation of water purifier | TBC |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Plumbing Inspection | TBC | |
| 2 | Final Electrical Inspection | TBC | |
| 3 | Aquisation of Power connection of homes and common area. | TBC | |
| 4 | Final Florring, Painting, Electrical & Plumbig Fixtures | TBC | |
| 5 | Final Architect inspection | TBC | |
| 6 | Acceptance Inspection - Client Inspection | TBC |