Home / Track Progress / Fairheaven

Fairheaven

Residential · Tambaram, Chennai

ArchitectAr. Rengarajan — VR Architectural Consultants
Structural EngineerPrakash Ravindran — VRP Structures
Project DirectorEr. Sivashankar Sivaraman — Base Solid
Project Engineer
Site photos

From the site

Milestone status

Activity log

Sprint 1 — Due diligence & design4 activities
S.NoActivityAssignedStatus
1 SWAT ANALYSIS Er. Sivashankar Sivaraman Completed
2 LEGAL DUE DILIGENCE Er. Sivashankar Sivaraman, ADV. Bhamini Manogaran & ADV. Sathish Kumar Completed
3 SOIL TESTING Er. Manikandan Srinivasan Completed
4 ARCHITECTURAL DRAWINGS Er. Sivashankar Sivaraman, Er. Manikandan Srinivasan & Mr. Rengarajan - VR Architectures Completed
Sprint 2 — Permits & foundation start6 activities
S.NoActivityAssignedStatus
1 ACQUISITION OF STRUCTURAL STABILITY REPORT Er. Sivashankar Sivaraman & Mr. Prakash - VRP Structures Completed
2 ACQUISITION OF BUILDING PERMIT Er. Sivashankar Sivaraman Completed
3 SITE MARKING Mr. Sivashankar Sivaraman Completed
4 BORE WELL Mr. Sivashankar Sivaraman Completed
5 ACQUISITION OF FOUNDATION ARCHITECTURAL & STRUCTURAL DRAWINGS Sivashankar Sivaraman & Mr. Prakash - VRP Structures Completed
6 POOJA Not Applicable Completed
Sprint 3 — Foundation & basement14 activities
S.NoActivityAssignedStatus
1 PILLING FOR FOUNDATON TBC
2 CONCRETING FOR FOUNDATION TBC
3 ACQUISITION OF BASEMENT ARCHITECTURAL & STRUCTURAL DRAWINGS TBC
4 ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS TBC
5 PILE CAP FABRICATION & SHUTTERING TBC
6 PILE CAP CONCRETING TBC
7 INSTALATION OF UG SUMP TBC
8 ESCAVATION TBC
9 Structural Inspection TBC
10 PLINTH BEAM TBC
11 BLOCK WORK TBC
12 TIE BEAM TBC
13 EARTH FILLING TBC
14 FLOOR CONCRETING TBC
Sprint 4 — Columns & roof slab 110 activities
S.NoActivityAssignedStatus
1 STEEL FABRICATION COLUMNS TBC
2 COLUMN MARKING FOR CONCRETING TBC
3 COLUMN CONCRETING TBC
4 ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS TBC
5 STAIRCASE MARKING TBC
6 FABRICATION FOR BEAM TBC
7 SHUTERING FOR ROOF SLAB TBC
8 FABRICATION FOR ROOF SLAB 1 TBC
9 Structural Inspection TBC
10 CONCRETING FOR ROOF SLAB TBC
Sprint 5 — Roof slab 210 activities
S.NoActivityAssignedStatus
1 STEEL FABRICATION COLUMNS TBC
2 COLUMN MARKING FOR CONCRETING TBC
3 COLUMN CONCRETING TBC
4 ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS TBC
5 STAIRCASE MARKING TBC
6 FABRICATION FOR BEAM TBC
7 SHUTERING FOR ROOF SLAB TBC
8 FABRICATION FOR ROOF SLAB 2 TBC
9 Structural Inspection TBC
10 CONCRETING FOR ROOF SLAB TBC
Sprint 6 — Roof slab 310 activities
S.NoActivityAssignedStatus
1 STEEL FABRICATION COLUMNS TBC
2 COLUMN MARKING FOR CONCRETING TBC
3 COLUMN CONCRETING TBC
4 ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS TBC
5 STAIRCASE MARKING TBC
6 FABRICATION FOR BEAM TBC
7 SHUTERING FOR ROOF SLAB TBC
8 FABRICATION FOR ROOF SLAB 3 TBC
9 Structural Inspection TBC
10 CONCRETING FOR ROOF SLAB TBC
Sprint 7 — Roof slab 411 activities
S.NoActivityAssignedStatus
1 STEEL FABRICATION COLUMNS TBC
2 COLUMN MARKING FOR CONCRETING TBC
3 COLUMN CONCRETING TBC
4 ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS TBC
5 STAIRCASE MARKING TBC
6 FABRICATION FOR BEAM TBC
7 SHUTERING FOR ROOF SLAB TBC
8 FABRICATION FOR ROOF SLAB 4 TBC
9 Structural Inspection TBC
10 CONCRETING FOR ROOF SLAB TBC
11 Architecural Inspection TBC
Sprint 8 — Block work (Levels 1–3)18 activities
S.NoActivityAssignedStatus
1 Marking for Block Work Level 1 TBC
2 Sil & Windows Markings Level 1 TBC
3 Blockwork Execution Level 1 TBC
4 Laying of Lintel Beam Level 1 TBC
5 Super Structure Block Work Level 1 TBC
6 Marking for Block Work Level 2 TBC
7 Sil & Windows Markings Level 2 TBC
8 Blockwork Execution Level 2 TBC
9 Laying of Lintel Beam Level 2 TBC
10 Super Structure Block Work Level 2 TBC
11 Marking for Block Work Level 3 TBC
12 Sil & Windows Markings Level 3 TBC
13 Blockwork Execution Level 3 TBC
14 Laying of Lintel Beam Level 3 TBC
15 Super Structure Block Work Level 3 TBC
16 Instalation of Door Frame (Level 1, Level 2 & Level 3) TBC
17 Structural Stability Inspection TBC
18 Architecural Inspection TBC
Sprint 9 — Lift & electrical rough-in9 activities
S.NoActivityAssignedStatus
1 INSTALATION OF LIFT - Stage 1 TBC
2 ELECTRICAL PIPING & CONDUIT - Level 1 TBC
3 Fixing of Switch Metel Box, Distibution Box & Electrical Fixtures - Level 1 TBC
4 ELECTRICAL PIPING & CONDUIT - Level 2 TBC
5 Fixing of Switch Metel Box, Distibution Box & Electrical Fixtures - Level 2 TBC
6 Instalation of Door Frame internal Door & Washroom Doors (Level 1, Level 2, Level 3) TBC
7 ELECTRICAL PIPING & CONDUIT - Level 3 TBC
8 Fixing of Switch Metel Box, Distibution Box & Electrical Fixtures - Level 3 TBC
9 Button Marking for Plastering (Level 1, Level 2, Level 3) TBC
Sprint 10 — Internal plastering4 activities
S.NoActivityAssignedStatus
1 Internal Plastering - Level 1 TBC
2 Internal Plastering - Level 2 TBC
3 Internal Plastering - Level 3 TBC
4 Comon Area Platering (Level 1, Level 2, Level 3) TBC
Sprint 11 — Doors, putty & external plastering12 activities
S.NoActivityAssignedStatus
1 Instalation of Main Door - (Level 1, Level 2, Level 3) TBC
2 Internal Putty - (Level 1, Level 2, Level 3) TBC
3 Internal Primer Coat 1 - (Level 1, Level 2, Level 3) TBC
4 Internal Primer Coat 2 - (Level 1, Level 2, Level 3) TBC
5 Construction of parapet wall TBC
6 Inspection before plastering TBC
7 External Platering South Side TBC
8 External Platering West Side TBC
9 External Platering East Side TBC
10 External Platering North Side TBC
11 Instalation of internal Plumibing TBC
12 Internal Wiring - (Level 1, Level 2, Level 3) TBC
Sprint 12 — Water tank, flooring & fittings5 activities
S.NoActivityAssignedStatus
1 Instalation Water Tank TBC
2 Instation of Florring - (Level 1, Level 2, Level 3) TBC
3 External Plumbig TBC
4 Instation of Internal and Washroom Doors TBC
5 Instation of Windows and Grills TBC
Sprint 13 — Compound wall & car parking10 activities
S.NoActivityAssignedStatus
1 Marking for Compund wall TBC
2 Escavation of Compund Coloumns TBC
3 Fabrication for Footing TBC
4 Footing Concreting TBC
5 Fabrication for Column TBC
6 Compound Callumn Concreting TBC
7 Block Work for Column TBC
8 Compund Plastering TBC
9 Instation of Pavor Block in Car Parking TBC
10 Appliying for power connection for all booked customers TBC
Sprint 14 — Painting & finishing7 activities
S.NoActivityAssignedStatus
1 Internal Painting (Level 1, Level 2 & Level 3) TBC
2 Door Painting TBC
3 Grill Painting TBC
4 External painting TBC
5 Instalation of CCTV Cameras TBC
6 Landscaping TBC
7 Instation of water purifier TBC
Handover6 activities
S.NoActivityAssignedStatus
1 Plumbing Inspection TBC
2 Final Electrical Inspection TBC
3 Aquisation of Power connection of homes and common area. TBC
4 Final Florring, Painting, Electrical & Plumbig Fixtures TBC
5 Final Architect inspection TBC
6 Acceptance Inspection - Client Inspection TBC