| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | SWAT ANALYSIS | Sivashankar Sivaraman | Completed |
| 2 | LEGAL DUE DILIGENCE | Sivashankar Sivaraman, ADV. Bhamini Manogaran & ADV. Sathish Kumar | Completed |
| 3 | SOIL TESTING | Sivashankar Sivaraman | Completed |
| 4 | ARCHITECTURAL DRAWINGS | Sivashankar Sivaraman & Mr. Rengarajan - VR Architectures | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | ACQUISITION OF STRUCTURAL STABILITY REPORT | Sivashankar Sivaraman & Mr. Prakash - VRP Structures | Completed |
| 2 | ACQUISITION OF BUILDING PERMIT | Sivashankar Sivaraman | Completed |
| 3 | SITE MARKING | Mr. Sivashankar Sivaraman & Mr. Deepak Ayankalai | Completed |
| 4 | BORE WELL | Mr. Sivashankar Sivaraman & Mr. Deepak Ayankalai | Completed |
| 5 | ACQUISITION OF FOUNDATION ARCHITECTURAL & STRUCTURAL DRAWINGS | Sivashankar Sivaraman & Mr. Prakash - VRP Structures | Completed |
| 6 | POOJA | Not Applicable | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | PILLING FOR FOUNDATON | Mr. Sivashankar Sivaraman & Mr. Deepak Ayankalai | Completed |
| 2 | CONCRETING FOR FOUNDATION | Mr. Sivashankar Sivaraman & Mr. Deepak Ayankalai | Completed |
| 3 | ACQUISITION OF BASEMENT ARCHITECTURAL & STRUCTURAL DRAWINGS | Sivashankar Sivaraman & Mr. Prakash - VRP Structures | Completed |
| 4 | ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS | Sivashankar Sivaraman & Mr. Rengarajan - VR Architectures | Completed |
| 5 | PILE CAP FABRICATION & SHUTTERING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 6 | PILE CAP CONCRETING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 7 | INSTALATION OF UG SUMP | Mr. Sivashankar Sivaraman & Mr. Deepak Ayankalai | Completed |
| 8 | ESCAVATION | Mr. Sivashankar Sivaraman & Mr. Deepak Ayankalai | Completed |
| 9 | Structural Inspection | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Prakash - VRP Structures | Completed |
| 10 | PLINTH BEAM | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 11 | BLOCK WORK | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 12 | TIE BEAM | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 13 | EARTH FILLING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 14 | FLOOR CONCRETING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | STEEL FABRICATION COLUMNS | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 2 | COLUMN MARKING FOR CONCRETING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 3 | COLUMN CONCRETING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 4 | ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 5 | STAIRCASE MARKING | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 6 | FABRICATION FOR BEAM | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 7 | SHUTERING FOR ROOF SLAB | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 8 | FABRICATION FOR ROOF SLAB 1 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 9 | Structural Inspection | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Prakash - VRP Structures | Completed |
| 10 | CONCRETING FOR ROOF SLAB | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | STEEL FABRICATION COLUMNS | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 2 | COLUMN MARKING FOR CONCRETING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 3 | COLUMN CONCRETING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 4 | ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 5 | STAIRCASE MARKING | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 6 | FABRICATION FOR BEAM | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 7 | SHUTERING FOR ROOF SLAB | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 8 | FABRICATION FOR ROOF SLAB 2 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 9 | Structural Inspection | Mr. Sivashankar Sivaraman, Mr. Manikandan Srinivasan, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Prakash - VRP Structures | Completed |
| 10 | CONCRETING FOR ROOF SLAB | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | STEEL FABRICATION COLUMNS | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 2 | COLUMN MARKING FOR CONCRETING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 3 | COLUMN CONCRETING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 4 | ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 5 | STAIRCASE MARKING | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 6 | FABRICATION FOR BEAM | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 7 | SHUTERING FOR ROOF SLAB | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 8 | FABRICATION FOR ROOF SLAB 3 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 9 | Structural Inspection | Mr. Sivashankar Sivaraman, Mr. Manikandan Srinivasan, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Prakash - VRP Structures | Completed |
| 10 | CONCRETING FOR ROOF SLAB | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | STEEL FABRICATION COLUMNS | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 2 | COLUMN MARKING FOR CONCRETING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 3 | COLUMN CONCRETING | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 4 | ACQUISITION OF ELECTRICAL AND PLUMBING DRAWINGS | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan | Completed |
| 5 | STAIRCASE MARKING | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 6 | FABRICATION FOR BEAM | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 7 | SHUTERING FOR ROOF SLAB | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 8 | FABRICATION FOR ROOF SLAB 4 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 9 | Structural Inspection | Mr. Sivashankar Sivaraman, Mr. Manikandan Srinivasan, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Prakash - VRP Structures | Completed |
| 10 | CONCRETING FOR ROOF SLAB | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 11 | Architecural Inspection | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Marking for Block Work Level 1 | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 2 | Sil & Windows Markings Level 1 | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 3 | Blockwork Execution Level 1 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 4 | Laying of Lintel Beam Level 1 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 5 | Super Structure Block Work Level 1 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 6 | Marking for Block Work Level 2 | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 7 | Sil & Windows Markings Level 2 | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 8 | Blockwork Execution Level 2 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 9 | Laying of Lintel Beam Level 2 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 10 | Super Structure Block Work Level 2 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 11 | Marking for Block Work Level 3 | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 12 | Sil & Windows Markings Level 3 | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 13 | Blockwork Execution Level 3 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 14 | Laying of Lintel Beam Level 3 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 15 | Super Structure Block Work Level 3 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 16 | Instalation of Door Frame (Level 1, Level 2 & Level 3) | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 17 | Structural Stability Inspection | Mr. Sivashankar Sivaraman, Mr. Manikandan Srinivasan, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Prakash - VRP Structures | Completed |
| 18 | Architecural Inspection | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | INSTALATION OF LIFT - Stage 1 | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 2 | ELECTRICAL PIPING & CONDUIT - Level 1 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 3 | Fixing of Switch Metel Box, Distibution Box & Electrical Fixtures - Level 1 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 4 | ELECTRICAL PIPING & CONDUIT - Level 2 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 5 | Fixing of Switch Metel Box, Distibution Box & Electrical Fixtures - Level 2 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 6 | Instalation of Door Frame internal Door & Washroom Doors (Level 1, Level 2, Level 3) | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 7 | ELECTRICAL PIPING & CONDUIT - Level 3 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 8 | Fixing of Switch Metel Box, Distibution Box & Electrical Fixtures - Level 3 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 9 | Button Marking for Plastering (Level 1, Level 2, Level 3) | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Internal Plastering - Level 1 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 2 | Internal Plastering - Level 2 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 3 | Internal Plastering - Level 3 | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 4 | Comon Area Platering (Level 1, Level 2, Level 3) | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Instalation of Main Door - (Level 1, Level 2, Level 3) | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 2 | Internal Putty - (Level 1, Level 2, Level 3) | Mr. Deepak Ayankalai & Mr. Abdul Syed | Completed |
| 3 | Internal Primer Coat 1 - (Level 1, Level 2, Level 3) | Mr. Deepak Ayankalai & Mr. Abdul Syed | Completed |
| 4 | Internal Primer Coat 2 - (Level 1, Level 2, Level 3) | Mr. Deepak Ayankalai & Mr. Abdul Syed | Completed |
| 5 | Construction of parapet wall | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 6 | Inspection before plastering | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 7 | External Platering South Side | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 8 | External Platering West Side | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 9 | External Platering East Side | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 10 | External Platering North Side | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 11 | Instalation of internal Plumibing | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 12 | Internal Wiring - (Level 1, Level 2, Level 3) | Mr. Deepak Ayankalai, Mr. Satish & Mr. Velmurugan | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Instalation Water Tank | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 2 | Instation of Florring - (Level 1, Level 2, Level 3) | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 3 | External Plumbig | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 4 | Instation of Internal and Washroom Doors | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 5 | Instation of Windows and Grills | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Marking for Compund wall | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 2 | Escavation of Compund Coloumns | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 3 | Fabrication for Footing | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 4 | Footing Concreting | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 5 | Fabrication for Column | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 6 | Compound Callumn Concreting | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 7 | Block Work for Column | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 8 | Compund Plastering | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 9 | Instation of Pavor Block in Car Parking | Completed | |
| 10 | Appliying for power connection for all booked customers | Mr. Manikandan | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Internal Painting (Level 1, Level 2 & Level 3) | Mr. Deepak Ayankalai & Mr. Abdul Syed | Completed |
| 2 | Door Painting | Mr. Deepak Ayankalai & Mr. Abdul Syed | Completed |
| 3 | Grill Painting | Mr. Deepak Ayankalai & Mr. Abdul Syed | Completed |
| 4 | External painting | Mr. Deepak Ayankalai & Mr. Abdul Syed | Completed |
| 5 | Instalation of CCTV Cameras | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 6 | Landscaping | Mr. Deepak Ayankalai & Mr. Velmurugan | Completed |
| 7 | Instation of water purifier | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| S.No | Activity | Assigned | Status |
|---|---|---|---|
| 1 | Plumbing Inspection | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 2 | Final Electrical Inspection | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 3 | Aquisation of Power connection of homes and common area. | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 4 | Final Florring, Painting, Electrical & Plumbig Fixtures | Mr. Sivashankar Sivaraman, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 5 | Final Architect inspection | Mr. Sivashankar Sivaraman, Mr. Rengarajan, Mr. Deepak Ayankalai, Mr. Velmurugan & Mr. Manikandan Srinivasan | Completed |
| 6 | Acceptance Inspection - Client Inspection | Mr. Sivashankar Sivaraman, Mr. Manikandan, Mr. Deepak Ayankalai & Client | Completed |